Scope of Work
PDT Architects
Oyster River High School
16 July 1996


Gather Info/Exist Conditions Test Phase Update Phase
General
  • Coordinate with admin.
  • Review DRA Report
  • Review meeting notes
  • Meet with Committee twice
  • Present overall summary of work done to date
  • Coordinate with admin.
  • Meet with committee once
  • Final presentation to School Board
  • Coordinate with admin
Program
Building and Site
  • Compare DRA program with state and others
  • Concept Focus Group with key staff
  • Develop revised program of space needs: building and site
Building
  • Receive dwgs and respond
  • Verify existing conditions
  • Evaluate DRA design concept
  • Develop planning diagrams showing minimum/maximum costs
  • Revise cost estimate
  • Final drawings
Site
  • Receive dwgs and report
  • Verify existing conditions
  • Evaluate DRA design concepts
  • Evaluate DRA cost estimate
  • Develop planning diagrams showing minimum/maximum costs
  • Revise cost estimates
  • Final drawings


OROL Home CommonsCommons SchoolsSchools NewsstandNewsstand LibraryLibrary Voting BoothVoting Booth SoapboxSoapbox

Last update on 29-Mar-99 at 9:31 PM.

http://www.orol.org/schools/orhs/orgs/space_needs/pdt_scope.html

This page is edited by David K. Taylor. Please send questions or comments to editor@orol.org.