THE PROCESS
The QBS process usually involves the following steps:
- Owner prepares the preliminary scope of work, describing the
project to be built or problem to be solved. An independent
professional technical advisor may be retained by the Owner
to assist in the development of concise scope information. A
schedule of activities is formulated. (See Model Forms 1, 2).
- Owner invites qualified design firms to submit letters of
qualifications in a format provided by the owner.
Additionally, owners may place legal notices of invitation
in newspapers. (See Model Forms 3, 4)
- Owner reviews Letters of Qualifications, checks references,
ranks firms and selects 3 to 6 firms for interviews. All
other firms should be notified in writing of the selections.
Pre-interview site visits are arranged with the firms to be
interviewed to provide the opportunity for a better
understanding of the project requirements. (See Model Forms
5a, 5b, 6, 7a, 7b)
- Interviews are conducted. During this process, it is
important that the same questions be asked of each firm. In
fact, it is suggested that qualification criteria be made
available to each firm prior to being interviewed. (See Model
Form 8).
- Following the interviews, the owner ranks the firms in
accordance with a pre-determined ranking system. All
interviewed firms are notified in writing of the ranking.
(See Model Forms 9, 10).
- The number one ranked firm is asked to prepare a detailed
scope of work and meets with the owner to review / refine
the scope and to negotiate conditions of the contract and a
fair and equitable fee.
- If a satisfactory agreement can not be reached, negotiations
with that firm are suspended and negotiations area
commenced with the second ranked firm. The process
continues until an agreement is reached and formal contract
is executed.
MODEL FORMS
Model forms are offered to assist you in the selection
process. They can be used by merely filling in the missing
information earth can be altered to fit your particular
needs, based on the size and scope of your project.
OROL Home
Commons
Schools
Newsstand
Library
Voting Booth
Soapbox
Last update on 31-Mar-99 at 10:07 PM.
http://www.orol.org/schools/orhs/orgs/space_needs/qbs_process.html
This page is edited by
David K. Taylor. Please send questions or comments to
editor@orol.org.